This week we were able to pour our Third level and mezzanine slabs at the ESS Building. We have continued to frame our exterior and interior walls, waterproofing, sheathing and MEP Rough in at the AH and STEM Buildings. We have also been working on our EPDM Roofs at the STEM and AH building. Lastly, we are continuing to install site electrical, storm and sewer lines on site.