What’s Been Happening This Week !

Overhead Drone Photo

This week we were able to get our roof trusses set on the ESS Building. We were also able to get everything ready to start shingling our roof at the STEM and AH building on Monday. Our geothermal drilling has begun in the courtyard and we are half way through the courtyard. Our MEP in wall and overhead rough in is continuing throughout all three buildings, as is sheathing, waterproofing and framing.

 

STEM West Elevation Courtyard AH Roof STEM Cupola West AH Overhead Drone Photo Overhead Drone Photo Overhead Drone Photo Overhead Drone Photo Overhead Drone Photo Overhead Drone Photo Overhead Drone Photo

Tagged with: , , ,
Posted in Construction, Education, General

What’s Been Happening This Week !

Overhead Drone Photos

This week we were able to pour our Third level and mezzanine slabs at the ESS Building. We have continued to frame our exterior and interior walls, waterproofing, sheathing and MEP Rough in at the AH and STEM Buildings. We have also been working on our EPDM Roofs at the STEM and AH building. Lastly, we are continuing to install site electrical, storm and sewer lines on site.

Tagged with: , , ,
Posted in Construction, Education, General

What’s Been Happening This Week !

All 3 Buildings Drone Photo

This week we have been busy! We are have completed erecting our steel at the ESS Building and we are now detailing and installing our decking. We are prepped to pour our 2nd level slab on deck tomorrow. At the AH Building, we are continuing our interior and exterior framing, as well as our sheathing, waterproofing and MEP Rough in. We are also planning to fly the remaining roof trusses over the weekend! At the STEM Building, we are continuing our interior framing, MEP Rough in, and we have started work on our EPDM roof.

 

 

Tagged with: , , ,
Posted in Construction, Education, General

What’s Been Happening This Week !

Site Overview

This week we have started placing our Trusses at the AH Building and we’ve started our exterior framing. At the STEM Building we are still doing our MEP overhead rough in, interior framing, exterior sheathing, and waterproofing. At the ESS Building, we have been setting our structural steel, placing our metal deck, and detailing our steel. We are also continuing to grade the hill behind the ESS Building to prep for our retaining wall.

 

Tagged with: , , ,
Posted in Construction, Education, General, Uncategorized

What’s Been Happening This Week!

This week we began setting our structural steel at the ESS building. We were also able to pour our slab on deck, and begin our basement level interior framing at the Arts and Humanities building. At the STEM Building, we have continued our MEP Rough-in and interior framing, as well as our exterior sheathing. We have also begun to excavate for our segmented retaining wall and our storm and sewer piping is nearly complete!

Tagged with: , , ,
Posted in Construction, Education, General

What’s Been Happening This Week!

This week we were able to set our roof trusses at the STEM Building! We are also continuing our MEP Rough in and interior framing at the STEM Building. At the AH building we installed our fireproofing and we have been working on completing our steel detailing. At the ESS Building we have begun setting our first sequence of structural steel and are prepping to set our second sequence next week!

 

Tagged with: , , ,
Posted in Construction, Education, General

What’s Been Happening This Week!

This week was a busy one! We were able to pour our first floor slab on grade at the ESS Building, as well as our slab on grade and our mezzanine slab at the AH Building! We also received our trusses for the STEM building and are assembling them on the ground to then fly them to the roof. We have started our MEP rough in at the STEM Building as well. Geothermal piping has been completed in Parking Lot A, C, and D and our water line was completed.

 

Tagged with: , , ,
Posted in Construction, Education, General

What’s Been Happening This Week !

This week we have been installing our exterior and interior framing as well as our sheathing at the STEM Building. We are continuing to detail steel and place deck at the AH Building. At the ESS Building we are finishing up MEP underground rough in and preparing to pour our first floor slab next week! Lastly, we are continuing our horizontal geothermal piping at Parking Lot C and D.

Tagged with: , , ,
Posted in Construction, Education, General

What’s Been Happening This Week !

This week we have been able to start framing our exterior and interior walls at the STEM building. We have continued to set steel and deck at the AH building. We have nearly completed the underground MEP at the ESS building and began laying our CMU block. Lastly, our sanitary sewer lines, water lines, and geothermal piping is still in process.

 

Tagged with: , , ,
Posted in Construction, Education, General

What’s Been Happening This Week !

This week we were able to pour our upper level slab and our cupola slab at the STEM building, as well as begin our interior framing. We have continued to set steel at the AH building. Lastly, our footings are complete at the ESS building and our block mason has started laying block.

Tagged with: , , ,
Posted in Construction, Education, General

What’s Been Happening This Week !

This week we started setting our steel and were able to pour our basement slab at the Arts and Humanities Building. We’ve also been detailing steel and installing decking at the STEM building. The enrollment and student services building’s footings are almost complete and we are continuing to work on our geothermal piping in parking Lot’s A, C and D.

Tagged with: , , ,
Posted in Construction, Education, General

What’s Been Happening This Week !

This week we continued to set our steel at the STEM Building, we installed our underground piping at the AH Building and we will be pouring our basement slab on grade next Tuesday, our ESS footings are still on going, and lastly, our Geothermal piping is continuing in Parking Lot’s C and D.

Tagged with: , , ,
Posted in Construction, Education, General

What’s Been Happening This Week !

This week we were able to set all of our Seq. 1 and Seq. 2 Steel at the STEM building and we are currently installing decking. Our underground rough in is almost complete at the AH building and we will pour that slab next week. The ESS building footings and first floor walls are in the process of being poured. Lastly, our geothermal work is continuing in Parking Lot A and D.

 

Tagged with: , , ,
Posted in Construction, Education, General

What’s Been Happening This Week!

This week we were able to start setting our steel in the STEM building! We have also been working on our sanitary sewer line, geothermal borings have begun in parking lot D, AH basement walls are almost complete and we are running our underground plumbing and electrical lines in preparation to pour the basement slab, and lastly, our ESS footings and foundations are ongoing!

Tagged with: , , ,
Posted in Construction, Education, General

What’s Been Happening This Week !

This week we continued to pour our A&H Basement Walls, the ESS Building Footings, and we poured our STEM Building first floor slab! We’ve also continued our geothermal borings, sanitary sewer line installation and our water line.

Tagged with: , , ,
Posted in Construction, Education, General

What’s Been Happening This Week!

This week we have been working on our A&H Basement walls, our Geothermal piping is still in process and we are almost out of parking lot A, and our first floor slab at the STEM building is scheduled to be poured next week!

 

Tagged with: , , ,
Posted in Construction, Education, General

What’s been happening this week!

This week we have continued to install our sanitary sewer line, our water line, and our temporary electric. We’ve also begun our geothermal borings and are continuing to make progress on the STEM and A&H Building’s foundation walls.

Tagged with: , , ,
Posted in Construction, Education, General

What’s been happening this week!

This week we started our geothermal borings, continued to work on our footings at the A&H Building, and waterproofed and backfilled our basement walls at the STEM building.